China Refuses To Be Labelled As A Developed Country, It Is Happy As A Developing Nation // Dubai leadership forum maps priorities across key sectors // Agility agrees $581 million Tristar stake disposal to Aegis // Discover Surprising Southern Taiwan: Taiwan Tourism Administration Teams Up with Airlines & Travel Platforms with Multi-Million Rewards for International Travelers // Dubai Aerospace targets $2.1 billion dual-currency financing // Vatican confirms Pope Leo lung cancer after operation // UAE passport leads 2026 mobility ranking with 182 destinations // Legal & General shields sovereign bond purchases with futures // GFH Partners transfers Chicago logistics facility for $151 million // Amid Mounting Global Health Crises, World Health Summit Closes in Berlin with New Commitments // Zuckerberg reveals uncertainty behind Meta AI infrastructure commitment // Dubai studies underground network for three-dimensional transport system // Government debt is now the biggest threat to your wealth // Amit Shah’s Prediction Of Big Win For BJP In 2029 Lok Sabha Polls Has To Be Taken Seriously // Apple introduces HomeView and expands smart home range // Anthropic flags emerging self-replication risk across connected devices // Constitutional Immunity Cannot Shield An Election Chief’s Surrender To Executive // BR Shetty pursues $15bn damages against Bank of Baroda // OpenAI engineer charged over concealed executive room recorder // SMS Tan Kiat How, Rosianna Silalahi and Glenda Gloria to speak at PRISM Summit 2026 //

431 Infra Projects Show Cost Overrun Of Rs 4.82 Lakh Crore

NEW DELHI: As many as 431 infrastructure projects, each entailing an investment of Rs 150 crore or more, were hit by cost overrun of more than Rs 4.82 lakh crore in December 2023, an official report stated.

According to the Ministry of Statistics and Programme Implementation (MoSPI), which monitors infrastructure projects worth Rs 150 crore and above, out of 1,820 projects, 431 reported cost overrun and 848 projects were delayed.

“Total original cost of implementation of the 1,820 projects was Rs 25,87,066.08 crore and their anticipated completion cost is likely to be Rs 30,69,595.88 crore, which reflects overall cost overruns of Rs 4,82,529.80 crore (18.65 per cent of original cost),” the ministry’s latest report for December 2023 said. According to the report, the expenditure incurred on these projects till December 2023 is Rs 16,26,813.80 crore, which is 53 per cent of the anticipated cost of the projects.

However, it stated that the number of delayed projects decreased to 638, if delay is calculated on the basis of the latest schedule of completion. Out of the 848 delayed projects, 202 have overall delays in the range of 1-12 months, 200 have been delayed for 13-24 months, 323 projects for 25-60 months, and 123 projects have been delayed for more than 60 months.

The average time overrun in these 848 delayed projects stood at 36.59 months.

Reasons for time overrun, as reported by various project implementing agencies, include delay in land acquisition, in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delays in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems were among the other reasons.

The report also cited state-wise lockdowns due to COVID-19 (imposed in 2020 and 2021) as a reason for the delay in implementation of these projects.

It has also been observed that project executing agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it added.

With inputs from PTI.

The post 431 Infra Projects Show Cost Overrun Of Rs 4.82 Lakh Crore first appeared on Latest India news, analysis and reports on IPA Newspack.



Notice an issue?

Arabian Post strives to deliver the most accurate and reliable information to its readers. If you believe you have identified an error or inconsistency in this article, please don't hesitate to contact our editorial team at editor[at]thearabianpost[dot]com. We are committed to promptly addressing any concerns and ensuring the highest level of journalistic integrity.


Loading next story…
Just in:
Apple introduces HomeView and expands smart home range // GFH Partners transfers Chicago logistics facility for $151 million // Siam Paragon Bangkok International Fashion Week 2026 Unites Thai Designers to Drive the Future of Thailand’s Fashion Industry // Dubai leadership forum maps priorities across key sectors // OpenAI engineer charged over concealed executive room recorder // What If Anxiety Isn’t the Enemy? Bupa’s Health or Hype Video Series Explores the Body’s Response to Anxiety and New Approach to Workplace Burnout // Zuckerberg reveals uncertainty behind Meta AI infrastructure commitment // Anthropic flags emerging self-replication risk across connected devices // SMS Tan Kiat How, Rosianna Silalahi and Glenda Gloria to speak at PRISM Summit 2026 // BR Shetty pursues $15bn damages against Bank of Baroda // Discover Surprising Southern Taiwan: Taiwan Tourism Administration Teams Up with Airlines & Travel Platforms with Multi-Million Rewards for International Travelers // Government debt is now the biggest threat to your wealth // Legal & General shields sovereign bond purchases with futures // De Beers Group and The Government of The Republic of Botswana Extend Partnership with Olympic Champion Letsile Tebogo as Global Ambassador // China Refuses To Be Labelled As A Developed Country, It Is Happy As A Developing Nation // Agility agrees $581 million Tristar stake disposal to Aegis // Meta notifies 1,500 after GitHub code theft // Amit Shah’s Prediction Of Big Win For BJP In 2029 Lok Sabha Polls Has To Be Taken Seriously // Hong Kong regulator widens crackdown on IPO manipulation // Amid Mounting Global Health Crises, World Health Summit Closes in Berlin with New Commitments //