Cloud bucket flaw exposes silent data theft risk // Abu Dhabi starts new Saadiyat arts landmark // Dubai Holding eyes European data centre foothold // Ras Tanura crash kills Aramco personnel // Construction Management Awards 2026 – Now open for nomination Introduction of the Inaugural “Excellent Construction Safety Culture Award” Guides the Construction Industry Toward a New Milestone in Safety // TCL Supports “2026 Olympic Day cum Aichi-Nagoya Asian Games Fun Run”, Celebrating the Olympic Spirit with Athletes and the Public, and Offering Lucky Draw Prizes Worth Approximately HK$180,000 // Bracell Welcomes Fernando Branco’s Appointment to Lead ABAF and Reinforces Commitment to Sustainable Forestry Development in Bahia // Where Minds Meet to Launch Space Economy Association Off the Ground // Canvas breach sharpens UK campus cyber warning // PlayStation sales hit May low // Golden Bridge Real Estate Unveils Special Summer Offers Across Mashriq Elite Developments on July 1, 2026 // 5 Law Firms Making a Difference in Cincinnati // UAE anchors AI supply push in Washington // Why a Growing Number of German-Speaking Founders Are Choosing Dubai // Altcoins resist as Bitcoin absorbs June shock // 7 Law Firms Making a Difference in Charleston, SC // Vinmec Launches Vietnam’s First Integrated High-Tech Robotic Surgery Network, Establishing the Country’s First Multi-Connected Robotic Surgery Ecosystem // Bank of China (Hong Kong) x Television Broadcasts Limited (“TVB”) “Wealth Management Expo 2026” was Successfully Held // Cisco flaw hit before public warning // Oil gains as Gulf truce faces strain //

UAE delays launch of first nuclear reactor until 2018 – Energy

1494080107 Barakah plant nuclear UAE

The UAE on Friday delayed the start-up of its first nuclear reactor until next year for further safety checks because regulators have not yet granted an operating licence.

ADVERTISEMENT

The reactor, one of four being built at the $20-billion Barakah plant west of Abu Dhabi by a consortium led by Korea Electric Power Corp (KEPCO), had been due to begin operating this year.

But UAE nuclear regulators are still reviewing the operating licence application which was submitted in March 2015, Emirates Nuclear Energy Corp (ENEC) announced.

The delay aims “to ensure sufficient time for international assessments and adherence to nuclear industry safety standards, as well as a reinforcement of operational proficiency for plant personnel,” it said.

It said the new schedule reflects “lessons learned” from problems at South Korea’s New Gori No. 3 reactor. The Barakah plant is based on the same technology.

Senior nuclear experts from the International Atomic Energy Agency (IAEA) and the World Association of Nuclear Operators will conduct a series of voluntary assessments at Barakah, it added.

ENEC said the project, which will be operated by a joint venture with KEPCO, is now 79-percent complete.

When fully operational the four reactors are expected to provide up to a quarter of the UAE’s electricity.

There was no immediate comment from UAE nuclear regulators. The IAEA declined to comment.

Source link



Notice an issue?

Arabian Post strives to deliver the most accurate and reliable information to its readers. If you believe you have identified an error or inconsistency in this article, please don't hesitate to contact our editorial team at editor[at]thearabianpost[dot]com. We are committed to promptly addressing any concerns and ensuring the highest level of journalistic integrity.