Propertyfinder Group sees slower pace of unit handovers supporting Dubai market in 2017

Dubai, 22nd January 2017

Propertyfinder Group, the UAE’s leading real estate search portal, expects unit handovers in Dubai this year to be significantly lower than developers’ official projections, which should help support prices.

ADVERTISEMENT

While that may not be welcome news for off-plan investors hoping to soon pick up their keys, a more protracted handover schedule is better for market stability and in the long term helps protect the value of buyers’ investments.

“As most local developers rely on purchaser funds to complete the project, the construction timeline is at best an estimation – an estimation of how quickly they’ll sell as well as how quickly they can construct,” says Propertyfinder CCO, Lukman Hajje.

“Thankfully, these days, legislation requires that progress payments be linked to construction milestones. This offers purchasers some assurance that their funds must be used appropriately but it doesn’t protect them against slow project sales, hold-ups due to supplier, contractor and/or local government compliances issues or unfavorable market conditions. Any of which may force or encourage developers to delay handover.”

Nearly 15,000 new residential units were handed over in 2016, the highest level since 2012, industry consultants JLL revealed this month. Officially, 31,000 units are scheduled for completion this year, but like propertyfinder.ae, JLL also expects actual deliveries to be lower than announced.

Advertisement

“There is an internal market correction mechanism within the system. While not great for a purchaser who’s waiting to receive their shiny new property; whether by design or accident, delayed handovers have helped stabilise market fluctuations over the past decade and are expected to continue to play that role,” says Hajje.

“If there is sufficient demand from purchasers, sales will take place on schedule and projects will be handed over on time. If sales are slow, it will be largely due to market conditions and insufficient demand and as a result projects in the pipeline will take longer to sell and construct.”

Dubai residential prices made minor declines last year amid a slump in transactions, while an economic slowdown blighting the wider Gulf is dampening expectations for a rebound this year both in terms of Dubai property prices and sales activity.

Expo 2020 has long been forecast to boost Dubai’s property sector as construction of supporting infrastructure attracts a wave of new migrant workers and the exhibition itself lifts tourism numbers.

But at least half the major construction contracts awarded in Dubai from now on will likely fail to be finished in time for Expo 2020, MEED Projects reported this month.

Defining “major” as contracts worth more than $100 million, construction contracts completed over the past half-decade on average took 4.1 years, while the median duration was slightly shorter at 3.8 years, MEED estimates.

Simple maths shows that any new contracts are now unlikely to be finished in time for the Expo, which is slated to open in October 2020 and run until April 2021.

Of course, projects with an unmovable deadline such as the Expo are prioritised, but Dubai has much work to do ahead of the exhibition including building a 15-kilometre metro extension, the exhibition zones and nearby residential and mixed use projects, while other non-Expo developments such as the world’s tallest tower are also meant to beat the Expo deadline. 

-Ends-

© Press Release 2017

© Copyright Zawya. All Rights Reserved.

Via Zawya

ADVERTISEMENT

ADVERTISEMENT
Just in:
Leading the innovation in cryptocurrency trading, Qmiax Exchange has updated its OTC fiat exchange process // Municipalities Strengthen Ties Through New Secretariat // Italian Trade Agency unveils The Italian Taste Lab at FHA-F&B // LUX Celebrates A Century Of Unmatched Fragrance With “Still There” Campaign // New Report from Sinergia Animal Reveals Financial Institution’s Lag in Animal Welfare and Food System Sustainability Policies // Russian Luxury Spa in Dubai // Quality HealthCare Partners with eHealth to Enhance Patient Treatment Efficiency // Ten Perish in Mid-Air Collision of Malaysian Navy Helicopters // Zayed Center Unveils Roadmap for Global Heritage Preservation // Shaping the future crypto trading of compliance, Qmiax has launched a brand-new user interface and trading process // PM Narendra Modi’s Frustration Mounting On His Stronghold Too // Sasin Impact Entrepreneurship Week 2024: Inspire, Connect, Transform for a better, smarter, sustainable world // Andertoons by Mark Anderson for Tue, 23 Apr 2024 // Brazilian Fintech Giant Nubank Embraces Cryptocurrencies // Octa crypto snapshot: investors behavior predictions after Bitcoin halving // China Railway Construction Corporation: Breakthroughs in Early 2024 Drive the Railways Modernisation // Crypto Advocacy Groups Challenge SEC Rule // Dubai Airport Back in Business After Floods Disrupt Operations // VinFast officially signs agreements with 12 new dealers in the US // Migrity Business Talent Academy Announces Innovative AI Entrepreneurship //