Rooftop solar planning gaps behind power shortages

HDN/FPJ News |

The Keralam government has identified shortcomings in rooftop solar planning and inadequate battery storage as major factors aggravating the state’s electricity crisis, despite a substantial expansion in renewable energy generation.

The state produces an average of 5.95 million units of solar electricity daily, but insufficient storage infrastructure prevents surplus daytime generation from being transferred effectively to evening peak-demand hours.

The assessment has brought renewed attention to delays in establishing Battery Energy Storage Systems (BESS), which are considered essential for balancing electricity supply and consumption as rooftop solar installations multiply.

Although approval has been granted for storage facilities at six locations, only the installation at Mulleria in Kasaragod has been completed. Projects at Areekode are expected to become operational by January, while facilities at Mayilatti, Sreekandapuram and Pothencode could be ready by March.

Another installation is planned at Brahmapuram, while NTPC is considering battery storage infrastructure at its Kayamkulam thermal power station.

Electricity Minister Sunny Joseph said on Friday that the state could not depend entirely on rooftop solar generation because electricity requirements remain substantial after sunset. He emphasised the need for storage systems capable of preserving daytime production for consumption at night.

The government is examining decentralised battery installations involving local self-government institutions and cooperative organisations. Joseph said ₹100 crore had been allocated in the state Budget, although additional financing would be necessary to expand the programme.

Subsidies and bank loans are among the financing arrangements being considered to encourage community-level storage facilities.

The storage shortfall has become more significant as the number of electricity consumers generating rooftop solar power has increased sharply. Keralam had approximately 150,000 such consumers on March 31, 2025, compared with about 362,000 now.

These consumers, commonly described as prosumers, generate electricity for their own requirements and supply surplus production to the distribution network.

Under net metering arrangements, electricity exported during daylight hours is credited against electricity subsequently drawn from the grid. This substantially reduces bills for many households operating rooftop solar installations.

However, the Kerala State Electricity Board (KSEB) believes the arrangement has contributed to increased evening consumption because some prosumers have little financial incentive to restrict electricity usage during peak hours.

The board’s assessment does not establish that rooftop solar installations themselves have caused the shortage. Rather, the difficulty arises from the mismatch between generation patterns, consumption behaviour and the availability of storage infrastructure.

Official consumption figures underline the pressure facing electricity planners. Average daily electricity usage increased from 76.23 million units in July 2025 to 86.71 million units in July 2026, representing an increase of 10.48 million units.

Peak electricity demand rose even more sharply. The maximum requirement recorded during September increased from 4,480 megawatts in 2025 to 5,639 megawatts this year, a rise of 1,159 megawatts.

The mismatch between available supply and evening requirements forced the electricity authorities to introduce load-shedding measures during September to contain peak demand.

KSEB has also faced scrutiny over its electricity demand forecasts and procurement arrangements. The Kerala State Electricity Regulatory Commission questioned discrepancies between projected requirements and actual consumption, prompting the utility to revise its estimates.

For October, the board had projected maximum daily consumption of 93.4 million units, whereas actual demand reached 101.54 million units. However, evening peak demand remained below its forecast, highlighting difficulties in anticipating different consumption patterns.

The commission also questioned proposals involving expensive electricity purchases and asked the board to account for additional supplies expected through existing arrangements.

The government maintains that longer-term procurement agreements remain necessary because electricity generation within Keralam has failed to keep pace with consumption.

Joseph said electricity demand had increased by approximately 2,500 megawatts over the past decade, while additional generation capacity had expanded by only about 150 megawatts.

He also clarified that the government had not entered into an agreement with private power procurement platform GNA and had no immediate plans to proceed with the proposed arrangement.

The storage challenge extends beyond household electricity bills. Rooftop installations feed surplus generation into local distribution networks, where excessive daytime supply can create voltage management difficulties.

KSEB estimates have indicated that rooftop solar prosumers consume approximately 36 per cent of their generation directly, exporting the remaining electricity to the grid.

(The article ‘Rooftop solar planning gaps behind power shortages’ appeared first on Free Press Journal.)



Notice an issue?

Arabian Post strives to deliver the most accurate and reliable information to its readers. If you believe you have identified an error or inconsistency in this article, please don't hesitate to contact our editorial team at editor[at]thearabianpost[dot]com. We are committed to promptly addressing any concerns and ensuring the highest level of journalistic integrity.


Loading next story…