CR Longdation Aethereal Cybersecurity × Global Cybersecurity Alliance (GCSA) Join Hands to Establish the “AI and Cybersecurity Research Centre” // Motorola introduces Signature 27 flagship priced at $1,599 // Technology shares plunge as Nasdaq enters correction // Geely’s i-HEV Intelligent Hybrid Technology Offers a New Direction for Gasoline-Powered Vehicles // Asia Left Behind: Ten international companies have yet to report delivering on their cage-free egg pledges across the region // Millions Of Indians May Soon Be Deprived Of Government Assistance // Trump’s Iran War Has A Share Of Contribution To His Midterm Debacle // Miss Universe Hong Kong Jen Zhou Departs for Puerto Rico to Compete in the 75th Miss Universe World Final // Dubai boat show confirms international shipyard line-up for November // OpenAI introduces GPT-6 Cyber with restricted security access // APT29-linked campaign exploits outdated Apple and Android software // e-Crime Bureau Signs Cybersecurity Partnership With Smart Africa, Reinforcing Its Global Expansion // Ningbo Consensus on Collaborative Development released at 2026 Global Mayors Dialogue · Ningbo // The “1st Greater Bay Area Health and Longevity Summit & Awards Ceremony” concludes successfully in Macao // Oil advances towards $100 as tanker attacks persist // OpenAI abandons secrecy agreements for future data centres // Xi Jinping Preparing For A Trilateral Summit With Trump And Putin At APEC Summit On Nov 18-19 // Kochi police detain two actors over bid to honey trap doctor // Geely’s i-HEV Intelligent Hybrid Technology Offers a New Direction Vision for Gasoline-Powered Vehicles // Dubai details five-year visa benefits for returning visitors //

DEWA completes 53% of M-Station expansion

M-Station is largest power plant in the UAE with total cost reaching AED 11.62 billion and will produce 2,760MW on completion

Dubai, UAE, 27 December 2016

Dubai Electricity and Water Authority (DEWA) has announced that it has completed 53% of the M-Station expansion project. The M-Station is the newest and largest power production and water desalination plant in the UAE. DEWA completed 3.9 million safe man-hours without any injuries.

DEWA is set to inaugurate two gas turbine generators on 31 May 2017, which will be followed by the addition of two heat recovery steam turbine generators and one back-pressure steam turbine on 30 April 2018. This will increase the plant’s thermal efficiency from 82.4% to 85.8%, which is considered one of the highest thermal-efficiency rates in the world.

The total cost of M-Station will be AED 11.62 billion. It was launched in 2013 at a cost of AED 10.15 billion, and the estimated cost of the expansion project is AED 1.47 billion. The project will be completed and delivered by end of April 2018.

The expansion project includes new power generation units with a capacity of 700MW to be added to the current capacity of the station to eventually produce 2,760MW by 2018. Its current total capacity is 2,060MW of electricity and 140 million imperial gallons of water per day (MIGD). The station adopts the highest levels of availability, reliability, and efficiency, using the most advanced technologies in the world.

HE Saeed Mohammed Al Tayer, MD & CEO of DEWA, was briefed by representatives from Siemens on the project including its operational process and completion. DEWA has appointed Mott MacDonald as the consultancy company of the project. Nasser Lootah, Executive Vice President of Generation at DEWA, and Mansoor Al Suwaidi, Vice President for Projects Generation at DEWA, joined HE Al Tayer during the tour.

The M-Station is equipped with the latest and most advanced technological systems. It was launched in 2013 at a cost of AED 10.15 billion. This includes AED 6.2 billion for electricity to provide 2060MW through 6 Siemens (F) model gas turbines with a capacity of 234MW each, 6 heat recovery steam turbine generators, and 3 back-pressure steam turbines with a capacity of 218MW each. The project has been completed in phases since mid-2010. The desalination cost is AED 3.95 billion using 8 desalination units with multi-stage flash distillation (MSF) technology, with a capacity of 17.5 million MIGD for each unit, with a total of 140 million gallons per day. There are two dual-fuel fired auxiliary boilers of 390 tonnes per hour and 16 fuel oil storage tanks each with a capacity of 20,000 cubic metres. The total fuel storage tank’s capacity is 320,000 cubic meters.

Advertisement

DEWA continues to build a strong infrastructure to enhance its installed capacity, which is currently 9,900MW of electricity and 470 million MIGD. DEWA enhanced its efficiency rate between 84-90%, while production capacity improved by 27% in 2015 compared to 2006, with the use of efficient technologies in electricity production and desalination.

DEWA has achieved promising success in energy transmission and distribution. DEWA currently operates 21 (400kV) substations, and 222 (132kV) substations.

-Ends-

For more information, please contact: 
Orient Planet PR and Marketing Communications
P.O. Box: 500266
Dubai, United Arab Emirates 
Tel:  00971 4 456 2888 
Fax: 00971 4 454 9528
Email: [email protected]
Website: www.orientplanet.com

© Press Release 2016

© Copyright Zawya. All Rights Reserved.

Via Zawya



Notice an issue?

Arabian Post strives to deliver the most accurate and reliable information to its readers. If you believe you have identified an error or inconsistency in this article, please don't hesitate to contact our editorial team at editor[at]thearabianpost[dot]com. We are committed to promptly addressing any concerns and ensuring the highest level of journalistic integrity.


Loading next story…
Just in:
Miss Universe Hong Kong Jen Zhou Departs for Puerto Rico to Compete in the 75th Miss Universe World Final // Oil advances towards $100 as tanker attacks persist // Asia Left Behind: Ten international companies have yet to report delivering on their cage-free egg pledges across the region // Ousted top Kochi cop gets IG post // CR Longdation Aethereal Cybersecurity × Global Cybersecurity Alliance (GCSA) Join Hands to Establish the “AI and Cybersecurity Research Centre” // Dubai boat show confirms international shipyard line-up for November // APT29-linked campaign exploits outdated Apple and Android software // Oil and chip shares retreat after Democratic victories // Trump’s Iran War Has A Share Of Contribution To His Midterm Debacle // OpenAI abandons secrecy agreements for future data centres // Xi Jinping Preparing For A Trilateral Summit With Trump And Putin At APEC Summit On Nov 18-19 // Geely’s i-HEV Intelligent Hybrid Technology Offers a New Direction for Gasoline-Powered Vehicles // OpenAI introduces GPT-6 Cyber with restricted security access // Emaar approves Development buyout ahead of planned delisting // UK air traffic outage inflicted £33m financial losses // Dubai details five-year visa benefits for returning visitors // Kochi police detain two actors over bid to honey trap doctor // The “1st Greater Bay Area Health and Longevity Summit & Awards Ceremony” concludes successfully in Macao // Hong Kong mandates crypto transaction disclosures to tax authorities // Meraas showcases five residential zones at Dubai Design Week //